Report Card: Western treatment plant 5 West nutrient removal plant (Werr… B
Minor Issues
Original Budget
$290m
Current Cost
$332m
Cost Overrun
14.3%
41m
Schedule
+3 months
| Sector | Water |
| Responsible Entity | Melbourne Water Corporation |
| Status | In Progress |
| Original Completion | 28 Sep 2025 |
| Current Completion | 28 Dec 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.