Original TEI
$290.3m
Current TEI
$331.7m
Cost Overrun
+$41.4m
+14.3%
Schedule Overrun
3.0 months
Original: Sep 2025 → Dec 2025
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The estimated completion date has been revised to quarter 2 2025-26 to align with a revised project schedule.