Original Budget
$6,300m
Current Cost
$10,200m
Cost Overrun
61.9%
3,900m
Schedule
+30 months
Sector Transport
Responsible Entity Major Transport Infrastructure Authority
Status In Progress
Program Big Build
Original Completion 30 Jun 2023
Current Completion 31 Dec 2025
Scope Changes 0 recorded
Cost RAG Off Track
Time RAG Off Track
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.