Original Budget
$428m
Current Cost
$841m
Cost Overrun
96.7%
414m
Schedule
On Time
Sector Water
Responsible Entity Greater Western Water
Status In Progress
Original Completion Not specified
Current Completion Not specified
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.