Original Budget
$108m
Current Cost
$131m
Cost Overrun
21.0%
23m
Schedule
On Time
Sector Water
Responsible Entity Melbourne Water Corporation
Status In Progress
Original Completion 28 Sep 2024
Current Completion Not specified
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.