Original Budget
$543m
Current Cost
$564m
Cost Overrun
3.9%
21m
Schedule
+6 months
| Sector | Health & Human Services |
| Responsible Entity | Department of Health |
| Status | Completed |
| Original Completion | 31 Dec 2022 |
| Current Completion | 30 Jun 2023 |
| Scope Changes | 0 recorded |
| Cost RAG | At Risk |
| Time RAG | At Risk |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.