Original Budget
$6,522m
Current Cost
$6,449m
Cost Overrun
-1.1%
-73m
Schedule
On Time
Sector Transport
Responsible Entity Department of Transport and Planning
Status In Progress
Original Completion 28 Jun 2030
Current Completion 28 Jun 2030
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.