Original Budget
$429m
Current Cost
$421m
Cost Overrun
-1.7%
-7m
Schedule
+-9 months
Sector Transport
Responsible Entity Victorian Rail Track
Status In Progress
Original Completion 28 Jun 2026
Current Completion 28 Sep 2025
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.

View full project detail →