Original Budget
$106m
Current Cost
$123m
Cost Overrun
16.1%
17m
Schedule
+24 months
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Original Completion | 28 Dec 2024 |
| Current Completion | 28 Dec 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.