Report Card: Suburban Roads Upgrade – Northern Roads Upgrade and South E… D
Major Overruns
Original Budget
$2,523m
Current Cost
$3,318m
Cost Overrun
31.5%
795m
Schedule
+42 months
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Program | Big Build |
| Original Completion | 28 Dec 2025 |
| Current Completion | 28 Jun 2029 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.