Original TEI
$2523.0m
Current TEI
$3318.5m
Cost Overrun
+$795.5m
+31.5%
Schedule Overrun
42.0 months
Original: Dec 2025 → Jun 2029
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has increased by $795.487 million due to the addition of the Yan Yean Road Upgrade – Stage 2 initiative, as well as market escalation and utility relocation costs. The estimated completion date has been revised to quarter 4 2028-29 in line with a revised project schedule. The TEI includes $1 577.369 million of Commonwealth Government funding.