Report Card: Suburban Parks Program (Creating a Ring of New Parkland) (m… C
Significant Overruns
Original Budget
$192m
Current Cost
$212m
Cost Overrun
10.7%
21m
Schedule
+24 months
| Sector | Water |
| Responsible Entity | Department of Energy, Environment and Climate Action |
| Status | In Progress |
| Original Completion | 28 Jun 2024 |
| Current Completion | 28 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.