Original Budget
$128m
Current Cost
$129m
Cost Overrun
0.2%
0m
Schedule
On Time
Sector Other
Responsible Entity Other PNFC
Status In Progress
Original Completion 28 Sep 2024
Current Completion Not specified
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.