Report Card: South Dynon Train Maintenance Facility Stage 1 (statewide) B
Minor Issues
Original Budget
$122m
Current Cost
$122m
Cost Overrun
0%
Schedule
+33 months
| Sector | Transport |
| Responsible Entity | Victorian Rail Track (VicTrack) |
| Status | In Progress |
| Original Completion | 28 Sep 2023 |
| Current Completion | 28 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.