Original TEI
$247.8m
Current TEI
$1030.7m
Cost Overrun
+$782.9m
+315.9%
Schedule Overrun
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has increased by $875.648 million due to a revised project scope and review of planned spend mostly for the Growth Area North West Geelong program of works.