Original TEI
$192.0m
Current TEI
$326.3m
Cost Overrun
+$134.3m
+69.9%
Schedule Overrun
0.0 months
Original: Jun 2035 → Jun 2035
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has increased by $13.757 million, due to revised project scopes and increasing investment in relation to various sewer maintenance, renewals and reliability projects. The revised completion date is reflective of the revised project scope.