Original Budget
$318m
Current Cost
$320m
Cost Overrun
0.6%
2m
Schedule
On Time
Sector Health & Human Services
Responsible Entity Department of Health
Status In Progress
Original Completion 28 Jun 2024
Current Completion 28 Jun 2024
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.

View full project detail →