Original Budget
$1,750m
Current Cost
$2,100m
Cost Overrun
20.0%
350m
Schedule
+18 months
Sector Transport
Responsible Entity Department of Transport and Planning
Status In Progress
Original Completion 31 Dec 2023
Current Completion 30 Jun 2025
Scope Changes 0 recorded
Cost RAG Off Track
Time RAG Off Track
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.