Original Budget
$1,750m
Current Cost
$2,100m
Cost Overrun
20.0%
350m
Schedule
+18 months
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Original Completion | 31 Dec 2023 |
| Current Completion | 30 Jun 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | Off Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.