Report Card: Regional Rail Revival - Shepparton Line Upgrade - Stage 3 (… A
On Track
Original Budget
$399m
Current Cost
$408m
Cost Overrun
2.2%
9m
Schedule
On Time
| Sector | Transport |
| Responsible Entity | Victorian Rail Track |
| Status | In Progress |
| Program | Commonwealth Games Legacy |
| Original Completion | Not specified |
| Current Completion | Not specified |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History