Original TEI
$399.4m
Current TEI
$408.2m
Cost Overrun
+$8.8m
+2.2%
Schedule Overrun
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has increased by $8.802 million due to $14.200 million increase as a result of market escalation and complex signalling implementation, offset by $5.398 million decrease relating to expenditure being reclassified as operating instead of capital in line with accounting standards. The estimated completion date is to be confirmed when the co-ordination and scheduling of signalling works are finalised. The TEI includes $331.360 million of Commonwealth Government funding.