Original Budget
$563m
Current Cost
$872m
Cost Overrun
55.0%
310m
Schedule
On Time
Sector Transport
Responsible Entity Victorian Rail Track
Status In Progress
Original Completion 28 Mar 2026
Current Completion 28 Mar 2026
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.

View full project detail →