Original TEI
$1750.0m
Current TEI
$2100.0m
Cost Overrun
+$350.0m
+20.0%
Schedule Overrun
18.0 months
Original: Dec 2023 → Jun 2025
Cost Status
Off Track
Time Status
Off Track
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Contractors & Partners
Contractor Type Role Contract Value
UGL Limited Builder / Constructor Gippsland Line — VicConnect Alliance $530.0m
Decmil Builder / Constructor Gippsland Line — VicConnect Alliance
John Holland Builder / Constructor Bendigo Line — Track Upgrades $215.0m
CPB Contractors (CIMIC) Builder / Constructor Gippsland Line — Avon River Bridge $190.0m
McConnell Dowell Builder / Constructor Geelong Line — South Geelong to Waurn Ponds $371.0m
Downer Builder / Constructor Geelong Line — Waurn Ponds Station & Warrnambool Signalling $128.0m
Coleman Rail Builder / Constructor Shepparton Line — Stage 2 $163.0m
Arup Consultant Geelong Line — Design
WSP Australia Consultant Geelong Line — Design
Metadata

Upgrades to Ballarat, Bendigo, Geelong, Gippsland, and NE lines.