Report Card: Ready for school: Kinder for every three-year-old 2019-20 (… B
Minor Issues
Original Budget
$280m
Current Cost
$278m
Cost Overrun
-1.0%
-3m
Schedule
+24 months
| Sector | Education & Training |
| Responsible Entity | Department of Education |
| Status | In Progress |
| Original Completion | 28 Jun 2024 |
| Current Completion | 28 Jun 2026 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.