Report Card: Public Transport Ticketing Asset Renewal (statewide) C
Significant Overruns
Original Budget
$544m
Current Cost
$680m
Cost Overrun
25.2%
137m
Schedule
+18 months
| Sector | Transport |
| Responsible Entity | Victorian Rail Track |
| Status | In Progress |
| Original Completion | 28 Jun 2027 |
| Current Completion | 28 Dec 2028 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.