Original Budget
$544m
Current Cost
$680m
Cost Overrun
25.2%
137m
Schedule
+18 months
Sector Transport
Responsible Entity Victorian Rail Track
Status In Progress
Original Completion 28 Jun 2027
Current Completion 28 Dec 2028
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.