Public Transport Ticketing Asset Renewal (statewide)
Original TEI
$543.6m
Current TEI
$680.4m
Cost Overrun
+$136.7m
+25.2%
Schedule Overrun
18.0 months
Original: Jun 2027
→ Dec 2028
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.
Metadata
The TEI has increased by $136.735 million due to a program reset and includes savings identified from other rolling stock projects. The estimated completion date has been revised to quarter 2 2028-29 due to a program reset and the finalisation of design requirements with delivery partners.