Original Budget
$185m
Current Cost
$286m
Cost Overrun
54.8%
101m
Schedule
+27 months
| Sector | Housing |
| Responsible Entity | Homes Victoria |
| Status | In Progress |
| Original Completion | 28 Dec 2024 |
| Current Completion | 28 Mar 2027 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.