Original Budget
$11,100m
Current Cost
$26,100m
Cost Overrun
135.1%
15,000m
Schedule
+12 months
Sector Transport
Responsible Entity Major Transport Infrastructure Authority
Status In Progress
Program Big Build
Original Completion 31 Dec 2027
Current Completion 31 Dec 2028
Scope Changes 0 recorded
Cost RAG Off Track
Time RAG Off Track
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.