Original Budget
$11,100m
Current Cost
$26,100m
Cost Overrun
135.1%
15,000m
Schedule
+12 months
| Sector | Transport |
| Responsible Entity | Major Transport Infrastructure Authority |
| Status | In Progress |
| Program | Big Build |
| Original Completion | 31 Dec 2027 |
| Current Completion | 31 Dec 2028 |
| Scope Changes | 0 recorded |
| Cost RAG | Off Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.