New trains for Sunbury (metropolitan various)
Original TEI
$1788.8m
Current TEI
$1735.4m
Cost Overrun
$-53.4m
-3.0%
Schedule Overrun
24.0 months
Original: Dec 2024
→ Dec 2026
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.
Metadata
The TEI has decreased by $27.243 million due to budgeted amounts being reclassified as operating instead of capital expenditure, in line with accounting standards. The estimated completion date has been revised to quarter 2 2026-27 to reflect completion dates for residual works after Metro Tunnel completion.