Report Card: New schools construction (metropolitan various) To open in … A
On Track
Original Budget
$336m
Current Cost
$336m
Cost Overrun
0%
Schedule
On Time
| Sector | Education & Training |
| Responsible Entity | Department of Education |
| Status | In Progress |
| Original Completion | 28 Mar 2027 |
| Current Completion | 28 Mar 2027 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.