Original TEI
$934.6m
Current TEI
$934.6m
Cost Overrun
$0.0m
0.0%
Schedule Overrun
0.0 months
Original: Dec 2026 → Dec 2026
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has decreased by $13.104 million being reprioritised to the New schools construction 2023-24 program. The TEI includes $35.472 million from the Growth Areas Infrastructure Contribution. The estimated completion date has been revised to quarter 2 2026-27 in line with a staged project schedule for some projects in the package. The 2026 opening schools included in this initiative are on track for a Day 1 Term 1 opening.