Original Budget
$672m
Current Cost
$760m
Cost Overrun
13.2%
89m
Schedule
+12 months
| Sector | Education & Training |
| Responsible Entity | Department of Education |
| Status | In Progress |
| Original Completion | 28 Mar 2026 |
| Current Completion | 28 Mar 2027 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.