Original Budget
$1,500m
Current Cost
$1,800m
Cost Overrun
20.0%
300m
Schedule
+30 months
Sector Health & Human Services
Responsible Entity Department of Health
Status In Progress
Original Completion 30 Jun 2025
Current Completion 31 Dec 2027
Scope Changes 0 recorded
Cost RAG Off Track
Time RAG Off Track
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.