Report Card: Myki Replacement (Next Generation Ticketing) C
Significant Overruns
Original Budget
$548m
Current Cost
$685m
Cost Overrun
25.0%
137m
Schedule
+18 months
| Sector | Information Technology |
| Responsible Entity | Department of Government Services |
| Status | In Progress |
| Original Completion | 31 Dec 2025 |
| Current Completion | 30 Jun 2027 |
| Scope Changes | 0 recorded |
| Cost RAG | Off Track |
| Time RAG | Off Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.