Original Budget
$807m
Current Cost
$840m
Cost Overrun
4.1%
33m
Schedule
On Time
Sector Transport
Responsible Entity Victorian Rail Track
Status In Progress
Original Completion 28 Sep 2026
Current Completion 28 Sep 2026
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.