Original TEI
$807.3m
Current TEI
$840.3m
Cost Overrun
+$33.0m
+4.1%
Schedule Overrun
0.0 months
Original: Sep 2026 → Sep 2026
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has increased by $33.040 million due to $53.270 million of market escalation and complex signalling implementation, offset by a $20.230 million decrease relating to expenditure being reclassified as operating instead of capital in line with accounting standards. The estimated completion date has been revised to quarter 1 2026-27 in line with signalling works and the pipeline of projects schedule across the program. The TEI includes $528.116 million of Commonwealth Government funding.