Original Budget
$250m
Current Cost
$229m
Cost Overrun
-8.6%
-21m
Schedule
On Time
Sector Transport
Responsible Entity Victorian Rail Track
Status In Progress
Original Completion 28 Jun 2027
Current Completion Not specified
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.

View full project detail →