Original TEI
$123.0m
Current TEI
$124.6m
Cost Overrun
+$1.6m
+1.3%
Schedule Overrun
24.0 months
Original: Dec 2023 → Dec 2025
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has increased by $1.565 million due to market escalation.