Original Budget
$207m
Current Cost
$191m
Cost Overrun
-7.7%
-16m
Schedule
+-6 months
Sector Transport
Responsible Entity Department of Transport and Planning
Status In Progress
Original Completion 28 Jun 2026
Current Completion 28 Dec 2025
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.

View full project detail →