Original TEI
$206.7m
Current TEI
$190.8m
Cost Overrun
$-16.0m
-7.7%
Schedule Overrun
-6.0 months
Original: Jun 2026 → Dec 2025
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has decreased by $15.950 million due to $12.790 million of savings and $3.159 million due to budgeted amounts being reclassified as operating instead of capital expenditure, in line with accounting standards. The estimated completion date has been revised to quarter 2 2025-26 in line with a revised project schedule. The TEI includes $109.540 million of Commonwealth Government funding.