Original Budget
$117m
Current Cost
$120m
Cost Overrun
2.9%
3m
Schedule
+21 months
Sector Transport
Responsible Entity Department of Transport and Planning
Status In Progress
Original Completion 28 Jun 2024
Current Completion 28 Mar 2026
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.