Original TEI
$12642.5m
Current TEI
$13480.4m
Cost Overrun
+$837.9m
+6.6%
Schedule Overrun
0.0 months
Original: Dec 2025 → Dec 2025
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Contractors & Partners
Contractor Type Role Contract Value
John Holland Builder / Constructor Tunnels & Stations — Cross Yarra Partnership (PPP)
CPB Contractors (CIMIC) Builder / Constructor Rail Network Alliance — Systems & Infrastructure $1400.0m
Lendlease Builder / Constructor Tunnels & Stations — Cross Yarra Partnership (PPP) $6700.0m
Bouygues Construction Builder / Constructor Tunnels & Stations — Cross Yarra Partnership (PPP)
AECOM Consultant Rail Network Alliance — Design
Capella Capital PPP Partner Tunnels & Stations — Cross Yarra Partnership (PPP, Finance)
Bombardier Transportation (Alstom) Other Rail Network Alliance — Systems & Infrastructure
Metadata

The TEI has increased by $837.900 million, due to the additional payment of $745.000 million agreed between the State and Cross Yarra Partnership under the 2024 settlement agreement, State costs and the reprioritisation of savings from Dandenong Corridor Readiness Works (metropolitan various) ($18.476 million), Level Crossing Removal (metropolitan various) ($10.900 million) and Caulfield Reprioritisation Works ($8.524 million).