Original Budget
$758m
Current Cost
$809m
Cost Overrun
6.7%
51m
Schedule
+27 months
| Sector | Justice & Emergency |
| Responsible Entity | Department of Justice and Community Safety |
| Status | In Progress |
| Original Completion | 28 Mar 2025 |
| Current Completion | 28 Jun 2027 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.