Original Budget
$1,574m
Current Cost
$1,574m
Cost Overrun
0%
Schedule
On Time
Sector Culture, Sport & Community
Responsible Entity Other PNFC
Status In Progress
Original Completion 28 Dec 2028
Current Completion 28 Dec 2028
Scope Changes 0 recorded
Cost RAG Unknown
Time RAG Unknown
Cost History

Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.

View full project detail →