Original Budget
$5,000m
Current Cost
$5,000m
Cost Overrun
0%
Schedule
+48 months
| Sector | Transport |
| Responsible Entity | Suburban Rail Loop Authority |
| Status | In Progress |
| Program | Big Build |
| Original Completion | 31 Dec 2029 |
| Current Completion | 31 Dec 2033 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Off Track |
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.