Original TEI
$5000.0m
Current TEI
$5000.0m
Cost Overrun
$0.0m
0.0%
Schedule Overrun
48.0 months
Original: Dec 2029 → Dec 2033
Cost Status
Unknown
Time Status
Off Track
Cost History (TEI over time)

No TEI snapshots recorded yet.

Timeline Drift

No timeline snapshots recorded yet.

Metadata

Rail link to Melbourne Airport. Delayed by at least 4 years from original target.