Original Budget
$3,824m
Current Cost
$3,824m
Cost Overrun
0%
Schedule
+6 months
| Sector | Transport |
| Responsible Entity | Department of Transport and Planning |
| Status | In Progress |
| Program | Big Build |
| Original Completion | 30 Jun 2028 |
| Current Completion | 28 Dec 2028 |
| Scope Changes | 0 recorded |
| Cost RAG | On Track |
| Time RAG | On Track |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.