M80 Ring Road Upgrade (Greensborough)
Original TEI
$3824.2m
Current TEI
$3824.2m
Cost Overrun
$0.0m
0.0%
Schedule Overrun
5.9 months
Original: Jun 2028
→ Dec 2028
Cost Status
On Track
Time Status
On Track
Cost History (TEI over time)
Timeline Drift
No timeline snapshots recorded yet.
Contractors & Partners
| Contractor | Type | Role | Contract Value |
|---|---|---|---|
| Acciona Construction | Builder / Constructor | AMA Alliance | $766.0m |
| MACA Civil | Builder / Constructor | AMA Alliance | — |
| AECOM | Consultant | AMA Alliance — Design | — |
Metadata
The Commonwealth Government is contributing $5 billion to the North East Link program.