Original Budget
$297m
Current Cost
$296m
Cost Overrun
-0.5%
-2m
Schedule
+33 months
| Sector | Education & Training |
| Responsible Entity | Department of Education |
| Status | In Progress |
| Original Completion | 28 Sep 2024 |
| Current Completion | 28 Jun 2027 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |
Cost History
Data from Victorian Budget Paper 4 (State Capital Program) and VAGO Major Projects reports.