Original TEI
$297.1m
Current TEI
$295.5m
Cost Overrun
$-1.6m
-0.5%
Schedule Overrun
33.0 months
Original: Sep 2024 → Jun 2027
Cost Status
Unknown
Time Status
Unknown
Cost History (TEI over time)
Timeline Drift

No timeline snapshots recorded yet.

Metadata

The TEI has decreased by $1.605 million due to budgeted amounts being reclassified as operating instead of capital expenditure, in line with accounting standards. The estimated completion date has been revised to quarter 4 2026-27 due to land acquisition timelines.