Report Card: Kardinia Park Stadium Stage 5 Redevelopment (Geelong) B
Minor Issues
Original Budget
$142m
Current Cost
$142m
Cost Overrun
0%
Schedule
+15 months
| Sector | Other |
| Responsible Entity | Other public non-financial corporations |
| Status | In Progress |
| Program | Commonwealth Games Legacy |
| Original Completion | 28 Mar 2024 |
| Current Completion | 28 Jun 2025 |
| Scope Changes | 0 recorded |
| Cost RAG | Unknown |
| Time RAG | Unknown |